Project 1 - THREE STORY BUILDING PAINTING

Project 1 - THREE STORY BUILDING PAINTING

Image
Project Name THREE STORY BUILDING PAINTING Document Project Implementation Report
Category Darkness To Light Duration 2 months
Estimated Budget 600,000.00/= Actual Cost 661,400 .00/=
Sponsored By: Chilaw Marians of Australia Type 237,700 .00/=
Hon. VP Jan Samaranayake Type 162,000.00/=
Kansai Paint Type 125,400.00/=
Direct Fund Type 136,300.00/=
OB Coordinator(s) Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta
Sponsorship contact(s) CMOA

Overview and Objectives

This project was initiated by the Hon. Vice President of the Old Boys' Association Mr. Jan Samaranayake. He repaired the stairs of the three-story building and several other areas around it with his own money. Also, the Chilaw Marians of Australia made a generous contribution to the complete renovation of every part of the building.

Services/Materials Finished

  1. Existing roof rectification (to avoid rain coming interior).
  2. Suspended ceiling & painting the ceiling.
  3. Internal walls have been painted.
  4. A sink and a pantry and required plumbing with water supply and drainage.
  5. Painting the floor.
  6. Entrance pathway arrangement.

Costs

1. Costs involved with Material purchases.
Goods/Services Date Cost
1 Outside Paint Labour 18/12/2018 150,000.00
2 Inside Painting with Potty Work 19/12/2018 152,000.00
3 Paint Cost (Inside + Outside) (Sponsored by Kansai) 22/12/2018 125,400.00
4 Staircase Mason + Plastering + Painting (Sponsored by Mr. Jan Sammaranayake) 23/12/2018 162,000.00
5 Balance Payment for Final Touchers 23/12/2018 25,000.00
Total 661,400.00
2. Funding
Description Date Cost
1 Chilaw Marians of Australia 18/12/2018 237,700.00
2 Staircase Mason + Plastering + Painting (Sponsored by Mr. Jan Sammaranayake) 23/12/2018 162,000.00
3 Paint Cost (Inside + Outside) (Sponsored by Kansai) 22/12/2018 125,400.00
4 Darkness to Light Direct Funds 18/12/2018 136,300.00
Total 661,400.00