Project 2 - TWO STORY BUILDING PAINTING
Project Name | TWO STORY BUILDING PAINTING | Document | Project Implementation Report |
Category | Darkness To Light | Duration | 2 months |
Estimated Budget | 316,160.00/= | Actual Cost | 738,000 .00/= |
Sponsorship | Alumnus from England | Type | 316,160.00/= |
Kansai Paint | Type | 150,000.00/= | |
Direct Fund | Type | 271,840.00/= | |
OB Coordinator(s) | Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta | ||
Sponsorship contact(s) | Mr. Mangala's Friends from UK |
Overview and Objectives
A brilliant alumnus from England contributed to the renovation of the main building which is considered to be the identity of the school. Also, as usual, Kansai sponsored the coating.
Services/Materials Finished
- Existing roof rectification (to avoid rain coming interior).
- Suspended ceiling & painting the ceiling.
- Internal walls have been painted.
- A sink and a pantry and required plumbing with water supply and drainage.
- Painting the floor.
- Entrance pathway arrangement.
Costs
1. Costs involved with Hardware material purchases.
Goods/Services | Date | Cost | |
---|---|---|---|
1 | Inside painting labor charge | 18/12/2018 | 60,000.00 |
2 | Outside painting and Roof Painting Labor Charge | 19/12/2018 | 80,000.00 |
3 | Door Window Repairing with Roof | 20/12/2018 | 100,000.00 |
4 | Roof Flashing Work | 21/12/2018 | 140,000.00 |
5 | Meson Work | 22/12/2018 | 40,000.00 |
6 | Wiring (Casing work) Labour + Equipment | 23/12/2018 | 100,000 |
7 | Paint Cost (Inside + Outside + Roof) (Sponsored by Kansai) | 23/12/2018 | 150,000 |
8 | Door and Window Painting | 23/12/2018 | 68,000 |
Total | 738,000 |
2. Funding
Description | Date | Cost | |
---|---|---|---|
1 | Mr. Mangala's friends from UK | 18/12/2018 | 316,160.00 |
2 | Paint Cost (Inside + Outside) (Sponsored by Kansai) | 18/12/2018 | 150,000.00 |
3 | Darkness to Light Direct Funds | 18/12/2018 | 271,840.00 |
Total | 738,000.00 |