Project 10 - FLOOD MANAGEMENT PROJECT

Project Name | FLODD MANAGEMENT PROJECT | Document | Project Implementation Report |
Category | Darkness To Light | Duration | 2 months |
Estimated Budget | 10,000,000.00/= | Actual Cost | 10,000,000.00/= |
Sponsorship | Mr. Rohana Fernando (Access Engineering) | Type | 10,000,000.00/= |
OB Coordinator(s) | Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta | ||
Sponsorship contact(s) | Jan Samaranayake, Ramin Kurera, Salinda Silva |
Overview and Objectives
This project was initiated by Chilaw Marians of Australia and also they made a generous contribution to the complete renovation of every part of the building.
Services/Materials Finished
- Existing roof rectification (to avoid rain coming interior).
- Suspended ceiling & painting the ceiling.
- Internal walls have been painted.
- A sink and a pantry and required plumbing with water supply and drainage.
- Painting the floor.
- Entrance pathway arrangement.
Costs
- Costs involved with Hardware material purchases.
Goods/Services | Date | Cost | |
---|---|---|---|
1 | Update to Date Total Spend | 18/12/2018 | 10,000.00 |
Total | 10,000,000.00 |
Project Progress Update

Funding

BEFORE
AFTER

