Project 10 - FLOOD MANAGEMENT PROJECT

Image
Project Name FLODD MANAGEMENT PROJECT Document Project Implementation Report
Category Darkness To Light Duration 2 months
Estimated Budget 10,000,000.00/= Actual Cost 10,000,000.00/=
Sponsorship Mr. Rohana Fernando (Access Engineering) Type 10,000,000.00/=
OB Coordinator(s) Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta
Sponsorship contact(s) Jan Samaranayake, Ramin Kurera, Salinda Silva

Overview and Objectives

This project was initiated by Chilaw Marians of Australia and also they made a generous contribution to the complete renovation of every part of the building.

Services/Materials Finished

  1. Existing roof rectification (to avoid rain coming interior).
  2. Suspended ceiling & painting the ceiling.
  3. Internal walls have been painted.
  4. A sink and a pantry and required plumbing with water supply and drainage.
  5. Painting the floor.
  6. Entrance pathway arrangement.

Costs

  1.  Costs involved with Hardware material purchases.
Goods/Services Date Cost
1 Update to Date Total Spend 18/12/2018 10,000.00
Total 10,000,000.00

Project Progress Update