Project 11 - PARTITIONING OF MAIN HALL BUILDING
Project Name | PARTITIONING OF MAIN HALL BUILDING | Document | Project Implementation Report |
Category | Darkness To Light | Duration | 2 months |
Estimated Budget | 260,000.00/= | Actual Cost | 597,000.00/= |
Sponsorship | 99 O/L and 2002 A/L Batch | Type | 597,000.00/= |
OB Coordinator(s) | Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta | ||
Sponsorship contact(s) | Mr. Ramin |
Overview and Objectives
2002 A / L batch contributed to the process of partitioning the main hall building, another well-known building of the school, and Kansai Paints sponsored the paint.
Services/Materials Finished
- Existing roof rectification (to avoid rain coming interior).
- Suspended ceiling & painting the ceiling.
- Internal walls have been painted.
- A sink and a pantry and required plumbing with water supply and drainage.
- Painting the floor.
- Entrance pathway arrangement.
Costs
- Costs involved with Hardware material purchases.
Goods/Services | Date | Cost | |
---|---|---|---|
1 | Equipments and Labour Charges | 18/12/2018 | 280,000.00 |
2 | Other Equipments Charges | 18/12/2018 | 32,000.00 |
3 | Glass Cost | 18/12/2018 | 25,000.00 |
4 | Painting (Varnishing) – Labour & Material | 18/12/2018 | 260,000.00 |
Total | 597,000 .00 |
2. Funding
Description | Date | Cost | |
---|---|---|---|
1 | 99 O/L and 2002 A/L | 18/12/2018 | 260,000.00 |
2 | Darkness To Light Direct Funds | 18/12/2018 | 337,000.00 |
Total | 597,000.00 |