Project 8 - BATHROOM EQUIPMENT SET 3(Other Accessories)
Project Name | BATHROOM EQUIPMENT SET 3(Other Accessories) | Document | Project Implementation Report |
Category | Darkness To Light | Duration | 2 months |
Estimated Budget | 92,704.00/= | Actual Cost | 75,000.00/= |
Sponsorship | 92 A/L Batch | Type | 0.00/= |
Direct Fund | Type | 75,000.00/= | |
OB Coordinator(s) | Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta | ||
Sponsorship contact(s) | Mr. Ricky |
Overview and Objectives
92 A / L batch contributed to the complete renovation of the toilet by paying the labor charges, and Kansai Paints sponsored the paint.
Services/Materials Finished
- Existing roof rectification (to avoid rain coming interior).
- Suspended ceiling & painting the ceiling.
- Internal walls have been painted.
- A sink and a pantry and required plumbing with water supply and drainage.
- Painting the floor.
- Entrance pathway arrangement.
Costs
- Costs involved with Hardware material purchases.
Goods/Services | Date | Cost | |
---|---|---|---|
1 | Aluminum Doors & Windows | 18/12/2018 | 75,000.00 |
Total | 75,000.00 |
2. Funding
Description | Date | Cost | |
---|---|---|---|
1 | 89 O/L and 92 A/L | 18/12/2018 | 0.00 |
2 | Darkness To Light Direct Funds | 18/12/2018 | 75,000.00 |
Total | 75,000.00 |