Project 6 - BATHROOM EQUIPMENT SET 1 (Floor Tiles)

Image
Project Name BATHROOM EQUIPMENT SET 1 (Floor Tiles) Document Project Implementation Report
Category Darkness To Light Duration 2 months
Estimated Budget 144,375.00/= Actual Cost 125,000.00/=
Sponsorship Direct Fund Type 125,000.00/=
OB Coordinator(s) Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta

Overview and Objectives

88 A / L batch contributed to the complete renovation of the Bathroom Floor Tiles, another important piece of equipment of the school, and Kansai Paints sponsored the paint.

Services/Materials Finished

  1. Existing roof rectification (to avoid rain coming interior).
  2. Suspended ceiling & painting the ceiling.
  3. Internal walls have been painted.
  4. A sink and a pantry and required plumbing with water supply and drainage.
  5. Painting the floor.
  6. Entrance pathway arrangement.

Costs

  1.  Costs involved with Hardware material purchases.
Goods/Services Date Cost
1 Equipments Charges 18/12/2018 125,000.00
Total 125,000.00
2. Funding
Description Date Cost
1 Darkness To Light Direct Funds 18/12/2018 125,000.00
Total 125,000.00

Project Progress Update

Image

Funding

Image

BEFORE

AFTER