Project 13 - DEMOLISH UNWANTED CONSTRUCTIONS

Project Name | DEMOLISH UNWANTED CONSTRUCTIONS | Document | Project Implementation Report |
Category | Darkness To Light | Duration | 2 months |
Estimated Budget | 73,500.00/= | Actual Cost | 73,500.00/= |
Sponsorship | Direct Fund | Type | 73,500.00/= |
OB Coordinator(s) | Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta | ||
Sponsorship contact(s) | Jan Samaranayake, Ramin Kurera, Salinda Silva |
Overview and Objectives
92 A / L batch contributed to the complete renovation of the toilet by paying the labor charges, and Kansai Paints sponsored the paint.
Services/Materials Finished
- Existing roof rectification (to avoid rain coming interior).
- Suspended ceiling & painting the ceiling.
- Internal walls have been painted.
- A sink and a pantry and required plumbing with water supply and drainage.
- Painting the floor.
- Entrance pathway arrangement.
Costs
- Costs involved with Hardware material purchases.
Goods/Services | Date | Cost | |
---|---|---|---|
1 | Equipments Charges | 18/12/2018 | 73,500.00 |
Total | 73,500.00 |
Summary
Goods/Services | Cost | |
---|---|---|
1 | Materials | 75,000.00 |
Total | 75,000.00 |
Project Progress Update

Funding

BEFORE
AFTER