Project Name DEMOLISH UNWANTED CONSTRUCTIONS Document Project Implementation Report
Category Darkness To Light Duration 2 months
Estimated Budget 73,500.00/= Actual Cost 73,500.00/=
Sponsorship Direct Fund Type 73,500.00/=
OB Coordinator(s) Jan Samaranayake, Shalitha De Soysa, Chaminda Ukwatta
Sponsorship contact(s) Jan Samaranayake, Ramin Kurera, Salinda Silva

Overview and Objectives

92 A / L batch contributed to the complete renovation of the toilet by paying the labor charges, and Kansai Paints sponsored the paint.

Services/Materials Finished

  1. Existing roof rectification (to avoid rain coming interior).
  2. Suspended ceiling & painting the ceiling.
  3. Internal walls have been painted.
  4. A sink and a pantry and required plumbing with water supply and drainage.
  5. Painting the floor.
  6. Entrance pathway arrangement.

Costs

  1.  Costs involved with Hardware material purchases.
Goods/Services Date Cost
1 Equipments Charges 18/12/2018 73,500.00
Total 73,500.00
Summary 
Goods/Services Cost
1 Materials 75,000.00
Total 75,000.00